Trenchless Design Construction Management

Status: Completed 2010

Construction Cost: $168,274 (local funding)

Description: The scope of work performed for this project included the design, plan and specification development, contract administration and project inspection for the rehabilitation of a total of 4015 LF of existing sanitary sewer pipe and nine sanitary sewer manholes. Cured-in-Place Pipe rehabilitation materials utilized on this project included 4015 LF of 8-inch diameter CIPP, 8-inch diameter CIPP point repair, and 6-inch diameter top hat side service CIPP repair. The manhole rehabilitation materials utilized on the project included spray applied polymer monolithic lining as well as a composite CIPP manhole lining system.

© Copyright Reichhardt and Ebe