Road and Bridge Construction

Status: Design Completed 2010, Started Construction February 2011, Construction Completed August 2011

Cost: Engineers Estimate $2.2 Million

Description: The project consists of street improvements to Kok Road from 200 feet east of Fishtrap Creek to 17th Street. Work includes removal of existing pavement, curbs and sidewalks and grading. Storm drainage installation icludes both water quality and infiltration underdrain systems, a sanitary sewer gravity and force main, and water main replacement. Project includes placing gravel base, asphalt concrete paving, installing curbs, gutters, and sidewalks and landscaping.

© Copyright Reichhardt and Ebe